Updated August 2022

Current Projects

Here is a listing of the Municipality's progress on Capital Projects

Project

Description

Status

Road Improvements

Sections of Eric Radford Way, McManus Street, McMarmac Road, and Cochenour Beach Road will receive pavement improvements including new asphalt. 
Transfer Station Road will have the degraded asphalt surface removed and replaced with granular surfacing. 
Contract awarded. 
Expected construction in August 2026.
Residential access will be maintained. 

Road Maintenance Program

Public Works and contractors are undertaking street sweeping, potholing, patching, shouldering, crack sealing, and line marking at various locations across the Municipality. 
Commenced for Summer 2026. 
Ongoing works. 

Sidewalk Replacement

Various locations across Red Lake, Balmertown and Cochenour. 
Summer 2026
Affected residents will be notified prior. 

Curb and gutter replacements 

Various locations across Red Lake, Balmertown and Cochenour. 
Summer 2026
Affected residents will be notified prior. 

Drainage Improvements

Minor earthworks, drainage installations, and landscaping for various properties along Goldshore Road, Red Lake. 
Contract awarded. 
Expected construction in August 2026. 
Affected residents have been notified. 